Rough plan for 2011 project:

April - Project startup and focus on user involvement to get input, beginning development
May / June - Development (major changes)
July - Summer break
August (until festival) - Development (layout changes, localization, small fixes, stabilizing)

Iterations

We will use and work within named iterations of about 3 weeks each, which will make it clear when we expect things to be implemented (for example, layout work late in the project) and also easier to test (the tester will be able to see, what's been implemented during the iteration). The iterations are:
  • Iteration 1: 2. May - 20. May
  • Iteration 2: 23. May - 10. June
  • Iteration 3: 13. June - 1. July
  • Iteration 4: 4. July - 22. July
  • Iteration 5: 25. July - 12. August

Last edited May 3, 2011 at 11:20 AM by christerdk, version 4